Kipabiskau Regional Park Authority - Accessible Ball Court Development

Pleasantdale No. 398, Saskatchewan

completeRecreationRNIS
Federal contribution
$48,584
Federal share40%

of $121.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 6, 2022
20232024
Built

Approved 3 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
May 8, 2023(actual)
Construction end
Jan 16, 2024(actual)

Against the original forecast

  • Construction end7 months earlyforecast Aug 31, 2024

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64058 in the federal list. How to read these figures.