Rural Municipalilty of Biggar No. 347 - Palo Bridge Replacement

Biggar No. 347, Saskatchewan

completeHighways and RoadsRNIS
Federal contribution
$43,047
Federal share17%

of $258.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 25, 2023
2023
Built

Approved 4 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
RM of Biggar No. 347
Construction start
Oct 15, 2023(actual)
Construction end
Oct 30, 2023(actual)

Against the original forecast

  • Construction start5 months lateforecast May 1, 2023
  • Construction end4 weeks earlyforecast Nov 30, 2023

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64062 in the federal list. How to read these figures.