Back to projects

Purchase of an accessible vehicle to provide transit service in Oxbow and surrounding communities, Saskatchewan

Enniskillen No. 3, Saskatchewan

completePublic TransitRTSF
Federal contribution
$50,000
Federal share51%

of $98.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 10, 2024
202320242025
Built

Approved 16 months before the announcement.

Program
Permanent Public Transit Program
Construction start
Sep 30, 2023(actual)
Construction end
Jun 23, 2025(actual)

Against the original forecast

  • Construction start16 months lateforecast Jun 1, 2022
  • Construction end2.5 years lateforecast Dec 31, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64089 in the federal list. How to read these figures.