New multi-use active transportation corridor between Peachland and Goats Peak Regional Park, British Columbia
Federal contribution
$356,400
Federal share60%
of $594.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2024
202320242025
Built
Approved 20 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- District of Peachland
- Construction start
- Nov 1, 2024(actual)
- Construction end
- Jun 20, 2025(actual)
Against the original forecast
- Construction start18 months lateforecast May 1, 2023
- Construction end22 months lateforecast Aug 18, 2023
Also in Peachland
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64170 in the federal list. How to read these figures.