New multi-use active transportation corridor between Peachland and Goats Peak Regional Park, British Columbia

Peachland, British Columbia

completeActive TransportationATF
Federal contribution
$356,400
Federal share60%

of $594.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2024
202320242025
Built

Approved 20 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
District of Peachland
Construction start
Nov 1, 2024(actual)
Construction end
Jun 20, 2025(actual)

Against the original forecast

  • Construction start18 months lateforecast May 1, 2023
  • Construction end22 months lateforecast Aug 18, 2023