Trans Canada Trail Extension Through Lakeview Village Waterfront Park

Mississauga, Ontario

approvedActive TransportationATF
Federal contribution
$17.1M
$17,058,824
Federal share60%

of $28.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 17, 2023
today
2023202520272029
BuiltForecast

Approved 11 months before the announcement.

Program
Active Transportation Fund
Construction start
May 30, 2023(forecast)
Construction end
Mar 31, 2029(forecast)