Little River Pedestrian Crossing and Multi-use Trails
Federal contribution
$1.3M
$1,307,610
Federal share60%
of $2.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 6, 2023
2023202420252026
Built
Approved 11 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- District of Sooke
- Construction start
- Oct 12, 2023(actual)
- Construction end
- Feb 26, 2026(actual)
Against the original forecast
- Construction end6 weeks lateforecast Jan 15, 2026
Also in Sooke
- Highway 14 Corridor Improvements$30.2M
- T'Sou-ke Nation - Community Complex and Health Centre$3.9M
- Sooke - Otter Point Corridor Active Transportation Project - Sidewalks and Bike Lanes$1.5M
- Honour the Land: A Hybrid Stormwater Management System and Naturalized Greenspace for TSou-ke First Nation$1.0M
- Sooke - Sunriver Multi-use Sport Box$487.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64220 in the federal list. How to read these figures.