Construction of a Green Boardwalk
Federal contribution
$486,986
Federal share59%
of $830.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 12, 2025
202320242025
Built
Approved 2.3 years before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Municipality of Sacré-Coeur
- Construction start
- May 20, 2025(actual)
- Construction end
- Oct 31, 2025(actual)
Against the original forecast
- Construction start2 years lateforecast May 15, 2023
- Construction end2 years lateforecast Oct 30, 2023
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64238 in the federal list. How to read these figures.