Town of Lumsden James St South Pathways System, Lumsden, Saskatchewan

Lumsden, Saskatchewan

completeActive TransportationATF
Federal contribution
$110,664
Federal share60%

of $184.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 15, 2023
2023
Built

Approved 12 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Town of Lumsden
Construction start
Feb 10, 2023(actual)
Construction end
Sep 8, 2023(actual)

Against the original forecast

  • Construction start3 months earlyforecast May 2, 2023
  • Construction end8 weeks lateforecast Jul 12, 2023