School area road safety improvements to facilitate active school travel in Kingston, Ontario
Federal contribution
$142,198
Federal share36%
of $400.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 17, 2023
2023202420252026
Built
Approved 16 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- City of Kingston
- Construction start
- Jul 22, 2022(actual)
- Construction end
- Mar 25, 2026(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Aug 15, 2022
- Construction end4 months lateforecast Nov 30, 2025
Also in Kingston
- City of Kingston Third Crossing Bridge$60.0M
- Ministry of Transportation Ontario Eastern Region New Ferry Vessels$31.3M
- Kingston Wastewater Treatment Plant Upgrades$25.0M
- Isabel Bader Centre for the Performing Arts at Queen's University at Kingston$15.0M
- Long Range Battery Electric Conventional Transit Buses and Bio- Diesel/Hybrid Buses$12.3M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64450 in the federal list. How to read these figures.