School area road safety improvements to facilitate active school travel in Kingston, Ontario

Kingston, Ontario

completeActive TransportationATF
Federal contribution
$142,198
Federal share36%

of $400.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 17, 2023
2023202420252026
Built

Approved 16 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
City of Kingston
Construction start
Jul 22, 2022(actual)
Construction end
Mar 25, 2026(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Aug 15, 2022
  • Construction end4 months lateforecast Nov 30, 2025

Also in Kingston

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64450 in the federal list. How to read these figures.