Town of Whitecourt Centennial Park Pathway Rehabilitation

Whitecourt, Alberta

completeActive TransportationATF
Federal contribution
$1.2M
$1,183,344
Federal share60%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 26, 2024
2023202420252026
Built

Approved 23 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Town of Whitecourt
Construction start
May 1, 2025(actual)
Construction end
Feb 9, 2026(actual)

Against the original forecast

  • Construction start2.8 years lateforecast Jul 4, 2022
  • Construction end7 weeks earlyforecast Mar 31, 2026

Also in Whitecourt

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64464 in the federal list. How to read these figures.