Lorne Bridge Trail Realignment
Federal contribution
$316,972
Federal share60%
of $528.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 15, 2024
20232024
Built
Approved 24 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- City of Brantford
- Construction start
- Oct 13, 2023(actual)
- Construction end
- Jun 30, 2024(actual)
Against the original forecast
- Construction start13 months lateforecast Sep 1, 2022
- Construction end7 months earlyforecast Jan 31, 2025
Also in Brantford
- Laurier Brantford YMCA Athletics and Recreation Complex$16.7M
- Construction of Wayne Gretsky Centre Four-Pad Arena$13.0M
- Upgrade of the Water Treatment Plant$5.4M
- Enclosing Open Concept Classrooms; HVAC; Water filling Station; Hallway door hold open devices; Entrance door security access$4.7M
- Grand Riverview$4.4M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64496 in the federal list. How to read these figures.