Northern Rockies Parks and Trails Active Mobility
Northern Rockies, British Columbia
Federal contribution
$50,000
Federal share100%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 19, 2022
20232024
Built
Approved 6 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Regional Municipality of Northern Rockies
- Construction start
- Nov 29, 2022(actual)
- Construction end
- Jan 12, 2024(actual)
Against the original forecast
- Construction start7 months lateforecast May 1, 2022
- Construction end13 months lateforecast Nov 30, 2022