National Survey of School Travel Establishing a travel mode baseline for Canadian communities. Provincial Pilot, British Columbia
Federal contribution
$50,000
Federal share83%
of $60.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 19, 2022
2023202420252026
Built
Approved 6 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Green Communities Association
- Construction start
- Apr 1, 2022(actual)
- Construction end
- Mar 31, 2026(actual)
Against the original forecast
- Construction end3 years lateforecast Mar 31, 2023
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64535 in the federal list. How to read these figures.