New bike lane on existing roadway
Federal contribution
$64,500
Federal share60%
of $107.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2024
20232024
Built
Approved 2.1 years before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Township of Russell
- Construction start
- Aug 5, 2022(actual)
- Construction end
- Dec 31, 2022(actual)
Against the original forecast
- Construction start3 months lateforecast May 16, 2022
Also in Russell
- Upgrades to the Water Distribution System$4.5M
- Watermain Twinning and Water and Wastewater Servicing of Russell's Commercial Park$787.3K
- Reconstruction and Surface Treatment - Route 200$326.8K
- Rehabilitation of Embrun Bowling Hall Equipment$115.9K
- Purchase of hybrid vehicles to support an existing transit service for rural regions surrounding City of Ottawa, Ontario$75.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64564 in the federal list. How to read these figures.