Active Transportation Master Plan for the Municipality of Bluewater, Ontario
Federal contribution
$47,927
Federal share100%
of $47.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 19, 2024
20232024
Built
Approved 21 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Municipality of Bluewater
- Construction start
- Jun 28, 2022(actual)
- Construction end
- Dec 31, 2023(actual)
Against the original forecast
- Construction start2 months earlyforecast Sep 5, 2022
Also in Bluewater