Highway 35 Multi-use Pathway

Bulkley-Nechako, British Columbia

completeCapacity BuildingATF
Federal contribution
$50,000
Federal share56%

of $90.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 19, 2022
20232024
Built

Approved 6 months before the announcement.

Program
Active Transportation Fund
Construction start
Mar 1, 2023(actual)
Construction end
Jun 1, 2024(actual)

Against the original forecast

  • Construction start7 months lateforecast Aug 1, 2022
  • Construction end3 months lateforecast Mar 1, 2024

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64628 in the federal list. How to read these figures.