Various Hospital Upgrades - Labrador and Northern Peninsula Regions
Happy Valley-Goose Bay, Newfoundland and Labrador
Federal contribution
$248,000
Federal share80%
of $310.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 28, 2024
20232024
Built
Approved 2.2 years before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Government of Newfoundland and Labrador
- Construction start
- Nov 22, 2022(actual)
- Construction end
- Nov 20, 2023(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Dec 6, 2022
- Construction end3 weeks lateforecast Oct 31, 2023
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64675 in the federal list. How to read these figures.