Various Upgrades to Several Health Centres in Central Newfoundland
Baie Verte, Newfoundland and Labrador
Federal contribution
$628,000
Federal share80%
of $785.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
202320242025
Built
Approved 2.6 years before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Government of Newfoundland and Labrador
- Construction start
- Sep 1, 2022(actual)
- Construction end
- Apr 30, 2025(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2022
- Construction end2 months lateforecast Feb 28, 2025
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64679 in the federal list. How to read these figures.