Rural Municipality of Big Stick No. 141, Bridge Replacement

Big Stick No. 141, Saskatchewan

completeHighways and RoadsRNIS
Federal contribution
$161,874
Federal share17%

of $971.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 25, 2023
20232024
Built

Approved 4 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
RM of Big Stick No. 141
Construction start
Jan 8, 2024(actual)
Construction end
May 15, 2024(actual)

Against the original forecast

  • Construction start7 months earlyforecast Aug 1, 2024
  • Construction end11 months earlyforecast Mar 31, 2025

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64744 in the federal list. How to read these figures.