Rural Municipality of Big Stick No. 141, Bridge Replacement
Big Stick No. 141, Saskatchewan
Federal contribution
$161,874
Federal share17%
of $971.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 25, 2023
20232024
Built
Approved 4 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- RM of Big Stick No. 141
- Construction start
- Jan 8, 2024(actual)
- Construction end
- May 15, 2024(actual)
Against the original forecast
- Construction start7 months earlyforecast Aug 1, 2024
- Construction end11 months earlyforecast Mar 31, 2025
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64744 in the federal list. How to read these figures.