Cultural Hub at the Tom Davies Square
Federal contribution
$24.9M
$24,908,530
Federal share48%
of $51.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 4, 2024
today
202320242025202620272028
BuiltForecast
Approved 2.3 years before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- City of Greater Sudbury
- Construction start
- Aug 25, 2025(actual)
- Construction end
- Apr 20, 2028(forecast)
Against the original forecast
- Construction start3 months lateforecast Jun 2, 2025
Also in Greater Sudbury