Back to projects

Cultural Hub at the Tom Davies Square

Greater Sudbury, Ontario

underwayCultureGICB
Federal contribution
$24.9M
$24,908,530
Federal share48%

of $51.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 4, 2024
today
202320242025202620272028
BuiltForecast

Approved 2.3 years before the announcement.

Program
Green and Inclusive Community Buildings Program
Ultimate recipient
City of Greater Sudbury
Construction start
Aug 25, 2025(actual)
Construction end
Apr 20, 2028(forecast)

Against the original forecast

  • Construction start3 months lateforecast Jun 2, 2025

Also in Greater Sudbury

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64756 in the federal list. How to read these figures.