Glace Bay Youth and Community Centre
Federal contribution
$8.8M
$8,828,512
Federal share57%
of $15.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 11, 2022
today
20232024202520262027
BuiltForecast
Approved 2 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- New Dawn Enterprises Ltd.
- Construction start
- Oct 31, 2024(actual)
- Construction end
- Mar 31, 2027(forecast)
Also in Cape Breton
- Cape Breton Regional Municipality - Wastewater Treatment Infrastructure$39.2M
- Cape Breton University - Centre for Discovery and Innovation$20.0M
- Eskasoni First Nation Long Term Care Kiknu$19.7M
- Sydney Harbour West Wastewater Collection and Treatment$19.3M
- CBRM - Battery Electric Bus Purchase and Storage and Maintenance Facility - Phase 2$16.7M