Kebaowek First Nation Cultural Centre
Federal contribution
$9.0M
$8,969,796
Federal share67%
of $13.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 19, 2022
today
202320242025202620272028
BuiltForecast
Approved 3 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Kebaowek First Nation
- Construction start
- Oct 1, 2025(actual)
- Construction end
- Nov 17, 2027(forecast)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64818 in the federal list. How to read these figures.