2022-23 PEI TI Local Roads 2

Avondale, Prince Edward Island

completeHighways and RoadsRNIS
Federal contribution
$2.3M
$2,341,705
Federal share50%

of $4.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 12, 2022
202320242025
Built

Approved 4 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Aug 29, 2022(actual)
Construction end
Aug 6, 2025(actual)

Against the original forecast

  • Construction end3 months earlyforecast Oct 31, 2025

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64905 in the federal list. How to read these figures.