Back to projects

Tsiigehtchic Wellness Camp Remodel

Tsiigehtchic, Northwest Territories

underwayCultureCCRIS
Federal contribution
$22,500
Federal share75%

of $30.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 17, 2022
today
20232024202520262027
BuiltForecast

Approved 2 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Gwichya Gwich'in Band
Construction start
Jun 6, 2023(actual)
Construction end
Oct 31, 2026(forecast)

Against the original forecast

  • Construction start12 months earlyforecast Jun 1, 2024