Energy and Climate Retrofit of SLCN Cultural Centre & Community Hall Building

Saddle Lake, Alberta

completeOtherGICB
Federal contribution
$1.2M
$1,184,283
Federal share95%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 19, 2025
202320242025
Built

Approved 2.7 years before the announcement.

Program
Green and Inclusive Community Buildings Program
Ultimate recipient
Saddle Lake Cree Nation
Construction start
Oct 12, 2023(actual)
Construction end
Nov 30, 2024(actual)

Against the original forecast

  • Construction start6 months lateforecast Apr 1, 2023
  • Construction end8 months lateforecast Mar 31, 2024

Also in Saddle Lake

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65005 in the federal list. How to read these figures.