Upgrades to the water network and connection infrastructure (Honoré-Roy Street)
Vallée-des-Rivières, New Brunswick
Federal contribution
$339,187
Federal share40%
of $848.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 26, 2023
202320242025
Built
Approved 10 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Saint-Léonard
- Construction start
- Jun 1, 2023(actual)
- Construction end
- Mar 17, 2025(actual)
Against the original forecast
- Construction start5 months lateforecast Jan 1, 2023
- Construction end2 months lateforecast Dec 31, 2024