Upgrades to the water network and connection infrastructure (Honoré-Roy Street)

Vallée-des-Rivières, New Brunswick

completeDrinking WaterGIS
Federal contribution
$339,187
Federal share40%

of $848.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 26, 2023
202320242025
Built

Approved 10 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Saint-Léonard
Construction start
Jun 1, 2023(actual)
Construction end
Mar 17, 2025(actual)

Against the original forecast

  • Construction start5 months lateforecast Jan 1, 2023
  • Construction end2 months lateforecast Dec 31, 2024