Brookvale (Route 13) Active Transportation Corridor

Brookvale, Prince Edward Island

completeActive TransportationGIS
Federal contribution
$669,797
Federal share43%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 7, 2024
20232024
Built

Approved 19 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Oct 22, 2022(actual)
Construction end
Oct 29, 2022(actual)

Against the original forecast

  • Construction start2 months lateforecast Aug 15, 2022