Various School Ventilation Upgrades

Bishop's Falls, Newfoundland and Labrador

completeVentilationCVRIS
Federal contribution
$1.9M
$1,896,090
Federal share80%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2025
202320242025
Built

Approved 2.5 years before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Nov 1, 2022(actual)
Construction end
Aug 27, 2024(actual)

Against the original forecast

  • Construction end4 months earlyforecast Dec 31, 2024