Water, Sewer, & Road Upgrades

Triton, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$148,474
Federal share40%

of $371.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2025
202320242025
Built

Approved 2.5 years before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Triton
Construction start
Jul 23, 2024(actual)
Construction end
Oct 31, 2024(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 1, 2024
  • Construction end6 weeks earlyforecast Dec 15, 2024