Watermain Replacement Water Street Valley Road Intersection (2022)

Botwood, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$230,653
Federal share40%

of $576.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2025
202320242025
Built

Approved 2.3 years before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Botwood
Construction start
Jun 4, 2024(actual)
Construction end
Jul 22, 2024(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jul 1, 2024
  • Construction end4 months earlyforecast Nov 30, 2024

Also in Botwood