Cascumpec Intersection Realignment - Routes 12 and 172
Cascumpec, Prince Edward Island
Federal contribution
$304,688
Federal share27%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 7, 2024
20232024
Built
Approved 19 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Prince Edward Island Department of Transportation and Infrastructure
- Construction start
- Oct 11, 2022(actual)
- Construction end
- Nov 2, 2022(actual)
Against the original forecast
- Construction start4 weeks lateforecast Sep 15, 2022
- Construction end6 months earlyforecast May 8, 2023
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65160 in the federal list. How to read these figures.