Surrey Langley SkyTrain

Langley, British Columbia

underwayPublic TransitPTIS
Federal contribution
$552.9M
$552,920,566
Federal share39%

of $1.4B total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2021
ApprovedMay 18, 2023
today
20222024202620282030
BuiltForecast

Approved 22 months after the announcement.

Program
Public Transit Infrastructure Stream
Construction start
Aug 1, 2024(actual)
Construction end
Nov 30, 2029(forecast)

Against the original forecast

  • Construction start2 months earlyforecast Oct 1, 2024