Pasqua First Nation - New Spray Park
Pasqua First Nation, Saskatchewan
Federal contribution
$514,766
Federal share75%
of $686.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 6, 2023
2023202420252026
BuiltForecast
Approved 12 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Pasqua First Nation
- Construction start
- May 1, 2024(actual)
- Construction end
- Mar 31, 2026(forecast)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65209 in the federal list. How to read these figures.