Back to projects

Pheasant Rump Nakota First Nation - Cultural Centre

Pheasant Rump Nakota First Nation, Saskatchewan

completeCultureCCRIS
Federal contribution
$3.4M
$3,350,499
Federal share75%

of $4.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 6, 2023
202320242025
Built

Approved 12 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Jun 21, 2024(actual)
Construction end
Sep 27, 2025(actual)

Against the original forecast

  • Construction start9 months lateforecast Sep 30, 2023
  • Construction end3 months earlyforecast Dec 31, 2025

Also in Pheasant Rump Nakota First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65247 in the federal list. How to read these figures.