White Bear First Nation - Community Spray Park
White Bear First Nation, Saskatchewan
Federal contribution
$266,987
Federal share75%
of $356.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 6, 2023
20242025
Built
Approved 9 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- White Bear First Nation
- Construction start
- May 20, 2024(actual)
- Construction end
- Jun 30, 2025(actual)
Against the original forecast
- Construction end9 months earlyforecast Mar 31, 2026
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65250 in the federal list. How to read these figures.