Upgrade/Replacement of Watermain Main Street Circular Drive/Philride Drive/Oceanview Drive Intersections
Cottlesville, Newfoundland and Labrador
Federal contribution
$355,970
Federal share40%
of $889.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
202320242025
Built
Approved 2.3 years before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Cottlesville
- Construction start
- Jun 14, 2024(actual)
- Construction end
- Aug 28, 2024(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Jul 18, 2024
- Construction end4 weeks earlyforecast Sep 22, 2024