Michipicoten Community Centre Renovations
Michipicoten First Nation, Ontario
Federal contribution
$2.6M
$2,628,828
Federal share53%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 3, 2025
2022202320242025
BuiltForecast
Approved 2.4 years before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Michipicoten First Nation
- Construction start
- Nov 1, 2021(forecast)
- Construction end
- Nov 30, 2022(forecast)