Watermain Replacement

Miles Cove, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$199,139
Federal share22%

of $893.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2025
202320242025
Built

Approved 2.3 years before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Miles Cove
Construction start
Oct 18, 2023(actual)
Construction end
May 29, 2024(actual)

Against the original forecast

  • Construction start7 months lateforecast Apr 1, 2023
  • Construction end7 months earlyforecast Dec 31, 2024

Also in Miles Cove

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65308 in the federal list. How to read these figures.