Watermain Replacement
Miles Cove, Newfoundland and Labrador
Federal contribution
$199,139
Federal share22%
of $893.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
202320242025
Built
Approved 2.3 years before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Miles Cove
- Construction start
- Oct 18, 2023(actual)
- Construction end
- May 29, 2024(actual)
Against the original forecast
- Construction start7 months lateforecast Apr 1, 2023
- Construction end7 months earlyforecast Dec 31, 2024
Also in Miles Cove
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65308 in the federal list. How to read these figures.