RM of Wood River - Municipal Nuisance Ground ESA Phase II, CAP & Decommissioning of Existing Cell

RM of Wood River No. 74, Saskatchewan

completeSolid Waste ManagementGIS
Federal contribution
$50,861
Federal share40%

of $127.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 25, 2023
2023
Built

Approved 2 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Apr 1, 2023(actual)
Construction end
Nov 27, 2023(actual)

Against the original forecast

  • Construction end4 months earlyforecast Mar 31, 2024

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65316 in the federal list. How to read these figures.