Prohibition Creek Access Road - Construction

Norman Wells, Northwest Territories

completeDisaster MitigationGIS
Federal contribution
$17.1M
$17,113,943
Federal share75%

of $22.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 18, 2023
20232024
Built

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Nov 22, 2022(actual)
Construction end
Sep 15, 2024(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Oct 18, 2022
  • Construction end6 months earlyforecast Mar 31, 2025

Also in Norman Wells

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65390 in the federal list. How to read these figures.