Prohibition Creek Access Road - Construction
Norman Wells, Northwest Territories
Federal contribution
$17.1M
$17,113,943
Federal share75%
of $22.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 18, 2023
20232024
Built
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Government of Northwest Territories
- Construction start
- Nov 22, 2022(actual)
- Construction end
- Sep 15, 2024(actual)
Against the original forecast
- Construction start5 weeks lateforecast Oct 18, 2022
- Construction end6 months earlyforecast Mar 31, 2025
Also in Norman Wells
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65390 in the federal list. How to read these figures.