Conception Bay Highway Phase 1
Brigus, Newfoundland and Labrador
Federal contribution
$281,577
Federal share40%
of $703.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 5, 2024
202320242025
Built
Approved 2.2 years before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Brigus
- Construction start
- Jun 4, 2024(actual)
- Construction end
- Jul 17, 2025(actual)
Against the original forecast
- Construction end7 months lateforecast Dec 13, 2024
Also in Brigus
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65416 in the federal list. How to read these figures.