‘Building the Future’: Tofield Arena Retrofit

Tofield, Alberta

completeRecreationGICB
Federal contribution
$904,298
Federal share70%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 15, 2023
202220232024
Built

Approved 9 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Ultimate recipient
Town of Tofield
Construction start
Sep 30, 2021(actual)
Construction end
Jan 12, 2024(actual)

Against the original forecast

  • Construction start6 months earlyforecast Apr 1, 2022