TTR Developing an Active Transportation Strategy
Federal contribution
$50,000
Federal share100%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 17, 2023
20232024
Built
Approved 11 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Tootinaowaziibeeng Treaty Reserve No. 292
- Construction start
- Dec 21, 2022(actual)
- Construction end
- Sep 30, 2024(actual)
Also in Grandview