Emerging Cultures Innovation Centre in Saint-Camille

Saint-Camille, Quebec

completeOtherRNIS
Federal contribution
$467,322
Federal share29%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 6, 2025
202320242025
Built

Approved 2.2 years before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Nov 30, 2022(actual)
Construction end
Jun 25, 2024(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Oct 31, 2022
  • Construction end5 months earlyforecast Nov 30, 2024

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65721 in the federal list. How to read these figures.