1940712 Ontario Inc - Zero Emission Buses Planning
Federal contribution
$41,280
Federal share80%
of $51.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 13, 2024
2024
Built
Approved 19 months before the announcement.
- Program
- Zero Emission Transit Fund
- Ultimate recipient
- 1940712 Ontario Inc
- Construction start
- Feb 28, 2023(actual)
- Construction end
- Jan 30, 2024(actual)
Against the original forecast
- Construction start10 months lateforecast May 1, 2022
- Construction end20 months earlyforecast Sep 30, 2025
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65784 in the federal list. How to read these figures.