Back to projects

Capital Refurbishment of Existing Transit Fleet

Charlottetown, Prince Edward Island

completePublic TransitPTIS
Federal contribution
$172,500
Federal share50%

of $345.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 12, 2024
20232024
Built

Approved 21 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
City of Charlottetown
Construction start
Dec 1, 2023(actual)
Construction end
Mar 14, 2024(actual)

Against the original forecast

  • Construction end2 weeks earlyforecast Mar 31, 2024