Kapawe'no First Nation Band Office Energy Retrofit
Federal contribution
$1.2M
$1,169,815
Federal share100%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 25, 2024
202320242025
BuiltForecast
Approved 16 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Kapawe'no First Nation
- Construction start
- Jul 1, 2024(actual)
- Construction end
- May 31, 2025(forecast)
Against the original forecast
- Construction start12 months lateforecast Jul 1, 2023
Also in Grouard