Back to projects

Stream bank restoration, wetland rehabilitation and transformation of a previously developed, abandoned site into a public greenspace and trailhead at Birch island Creek

Happy Valley-Goose Bay, Newfoundland and Labrador

underwayOtherNIF
Federal contribution
$37,200
Federal share69%

of $54.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 16, 2026
today
20252026
BuiltForecast

Approved 14 months before the announcement.

Program
Natural Infrastructure Fund
Construction start
Nov 1, 2025(actual)
Construction end
Oct 31, 2026(forecast)

Against the original forecast

  • Construction start7 months earlyforecast Jun 15, 2026