District of West Vancouver Urban Forest Enhancements

West Vancouver, British Columbia

underwayOtherNIF
Federal contribution
$326,600
Federal share80%

of $408.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 19, 2025
today
20252026202720282029
BuiltForecast

Approved 3 months before the announcement.

Program
Natural Infrastructure Fund
Ultimate recipient
District of West Vancouver
Construction start
Apr 23, 2025(actual)
Construction end
Dec 31, 2028(forecast)

Against the original forecast

  • Construction start4 months earlyforecast Sep 1, 2025