Burnaby Transit Centre (BTC) Facility Improvement
Federal contribution
$17.8M
$17,781,836
Federal share40%
of $44.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2024
today
2024202520262027
BuiltForecast
Approved 9 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- TransLink
- Construction start
- Feb 26, 2024(actual)
- Construction end
- Apr 1, 2027(forecast)
Against the original forecast
- Construction start8 weeks lateforecast Jan 2, 2024
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66857 in the federal list. How to read these figures.