Burnaby Transit Centre (BTC) Facility Improvement

Burnaby, British Columbia

underwayPublic TransitPTIS
Federal contribution
$17.8M
$17,781,836
Federal share40%

of $44.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2024
today
2024202520262027
BuiltForecast

Approved 9 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
TransLink
Construction start
Feb 26, 2024(actual)
Construction end
Apr 1, 2027(forecast)

Against the original forecast

  • Construction start8 weeks lateforecast Jan 2, 2024

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66857 in the federal list. How to read these figures.